Å·ÃÀÈÕb´óƬ

Skip to Main Navigation
Results Briefs December 18, 2020

Powering up Vietnam with clean and affordable energy: The Trung Son Hydropower Plant development experience


Since becoming operational in 2017, the new 260-megawatt (MW) grid-connected Trung Son hydropower plant has supplied on average 1 billion kilowatt-hours (kWh) of electricity annually at a unit cost lower than power generated by other renewable sources or by coal. The hydropower plant reduced greenhouse gas (GHG) emissions by 1 million metric tons annually compared to a thermal plant supplying the same volume of electricity. The project has achieved the objective to restore livelihood of affected people equal or better than before the project with a majority of some 3,400 households directly affected by the project enjoyed better standards of living due to better access to electricity, road connectivity, and improved livelihoods.

Challenge

By the time the project was approved in 2011, the double-digit growth in power demand in Vietnam between 2010-2020 had had major implications for the environment, increasing the country¡¯s reliance on fossil fuels for power generation. Greenhouse gas (GHG) emissions from the power sector was estimated to surge from 30 million tons of carbon dioxideequivalent in 2009 to 200 million tons in 2025. At the same time, thermal power plants were among the largest contributors to local air pollution. Therefore, Vietnam¡¯s big challenge was to find alternative power sources that could meet the fast-growing demand in a sustainable manner. Trung Son Hydropower Project (TSHPP) was prioritized by the government of Vietnam as it is a least cost option and its low potential environmental and social impacts.

Image
An aerial shot of Trung Son Hydropower Plant

Approach

Å·ÃÀÈÕb´óƬ worked closely with the government of Vietnam and successfully developed a hydropower plant that was technically sound, economically viable, and in line with international best practices in environmental and social sustainability. Extensive preparation work, informed by robust analysis and expedited procurement, effective Bank implementation support and client¡¯s capacity building helped facilitate smooth implementation and avoid delays and cost overruns often seen in large-scale infrastructure projects. The project was designed to fit the country¡¯s circumstances while incorporating international best practices in both technical and environmental and social safeguard aspects. For example, TSHPP was among the first projects in Vietnam to have additional safety features, pursue health-related targets, and successfully implement a community livelihood improvement program. In addition, the inclusion of social and environmental objectives in the project¡¯s main outcome indicators¡ªwhich are often treated as secondary elsewhere¡ªhelped secure prior commitment and ensure their realization. The project also benefited from effective consultations with local people and authorities.


Image
1 billion+ kWh

The new 260-megawatt grid-connected Trung Son hydropower plant will supply 1 billion kilowatt-hours of electricity annually at a unit cost lower than power generated by other renewable sources or by coal.


Results

The project has achieved the following outcomes:

  • The new 260-megawatt (MW) grid-connected hydropower plant became operational in 2017 and as of October 2019, it had supplied 2.5 billion kilowatt-hours (kWh) of electricity at an average net present cost lower than power generated by other renewable sources or by coal, at US?4.0 per kWh compared to solar photovoltaic (PV) feed-in tariff (FIT) of US?9.35 per kWh and wind FIT at US?7.9¨C9.8 per kWh.
  • The TSHPP reduced GHG emissions by approximately 1 million metric tons annually compared to a thermal plant supplying the same volume of electricity.
  • The project increased local access to grid electricity in the affected areas from 30 percent in 2015 to 97 percent (about 800 households) in 2019.
  • As a well-designed and dispatchable plant during peak hours, the TSHPP provided a sizeable and reliable capacity to meet the power demand and contributed to stable electricity output to the Vietnamese power system which reduced the frequent interruptions associated with supply demand imbalance thus improving the overall quality of electricity supplied to consumers.
  • The plant¡¯s reservoir dedicated a space that could store 112 million cubic meters of water for flood control. During the intensive three-day heavy rain event in August 2018, for example, the plant helped reduce the peak flood inflow by twenty percent.
  • The agriculture-based livelihoods of approximately 10,600 people in over 3,400 households affected by the project were either restored or improved. They continued their main practice of growing rice, maize and cassava and expanded into animal husbandry. The majority of the affected people were from ethnic minorities and two-thirds of households in the project areas were considered poor.
  • The project generated significant economic activity in the project-affected areas with the emergence of several small and medium-scale enterprises selling bamboo and agricultural products in the project area and along the newly built access roads. The percentage of local households engaged in small business and commerce increased from 10.3 percent to 24.6 percent between 2015 and 2019.

Image
New houses in the resettlement area. Photo: Tran Hong Ky ? Å·ÃÀÈÕb´óƬ

World Bank Group Contribution

Å·ÃÀÈÕb´óƬ Group¡¯s International Bank for Reconstruction and Development (IBRD) provided a US$330 million loan out of a total of US$411 million needed for the project. The Bank also provided extensive analytical and technical assistance throughout the project cycle. 

Partners

In addition to the IBRD loan, the project received US$2 million from a grant by the Policy and Human Resources Development Fund to support project preparation.

Moving Forward

The transmission infrastructure of TSHPP has laid the foundation for the future development of small hydropower projects in the region. A new privately-owned hydropower plant has sed used TSHPP¡¯s transmission lines to evacuate the energy it produces to the grid.

TSHPP was one of the first large hydropower projects in Vietnam to meet the international criteria as assessed by the International Hydropower Protocol. It has served as a best practice for hydropower development in Vietnam. Experiences in developing TSHPP, particularly the innovative and effective approaches in addressing environmental and social issues, are shared internationally and adopted by other large World Bank-financed hydropower projects, such as the Upper Arun Hydro Project in Nepal.

Image
Local children in a classroom in the resettlement area. Photo: Erin Gamble ? Å·ÃÀÈÕb´óƬ

Beneficiaries

¡°We are happy with the support we received to settle down in the relocation sites. We were able to raise chickens better due to the training we got. Before, chickens were easy to get sick and died fast. Now we know how [to] keep them healthy and take care of them when they get sick. Which medicine to take; how to use it¡­ They taught us all. We even discussed among each other. In many cases, the sick birds will get better instead of dying. Wonderful!¡± (Female, Head of Chicken Raising Group, Lin Village, Trung Ly Commune).


MULTIMEDIA

Image
click
The project aimed to improve health conditions for workers and communities affected in the project area.